The Project That Shipped and Nobody Used
Hello Learners,
This is Learn Leadership. Every issue takes one thing that quietly goes wrong between managers and their teams, shows it happening through a real story, and leaves you with something to try this week.
Today it's the project that launched on schedule and then sat untouched by the people it was built for. You'll get a five-question assumption check to run in your next requirements meeting.
Launch day, and eleven people logged in
Sofia's team launched the new job-tracking app at 7:00 on a Monday in June. It had taken eight months and cost about $180,000. It was built for 140 field technicians so they could update job status from the site in real time.
By 5:00 that afternoon, eleven technicians had logged in. Four weeks later, six were using it in a typical week. Everyone else was still texting the dispatch office and filling in the shared spreadsheet at the end of the day, exactly as before.
The app worked, and every feature passed testing. Technicians still couldn't use it where they actually did their jobs, and nobody found that out until it was live.
Six weeks before launch
Six weeks out, user acceptance testing went well. Twelve people from the dispatch office worked through 40 test scripts on their desktop screens and signed them all off. The demo for the operations director ran without a hitch.
Look at who did that testing. Dispatchers sit at desks with two monitors and a fast connection. Technicians work in basements, plant rooms, and car parks, on company phones, often with gloves on.
Nobody tested the app on a phone in a plant room. It wasn't in the test plan, because the test plan was written from the requirements, and the requirements never mentioned phones.
So the testing confirmed exactly what it was set up to confirm. The app did what the document said. Every green tick on that sign-off sheet was accurate, and none of them answered the one question that mattered: would a technician on site use it?
The signal everyone saw
Three weeks before launch, Sofia ran a pilot with five technicians. Two of them told her they'd "fill it in back at the depot." The support lead logged a ticket saying technicians couldn't sign in on-site because the company phones had no VPN profile.
Both got filed as training issues. The plan was a better user guide and a reminder email.
This is how warning signs usually die. They arrive informally, they sound minor, and they get routed to whoever can close them fastest.
NASA's Mars Climate Orbiter was lost in September 1999 after ground software sent thruster data in pound-force seconds to a system that expected newton-seconds. A NASA safety review of the loss notes that the navigation team discussed concerns about the trajectory during the cruise to Mars and that those concerns were never properly resolved before arrival.
Sofia's pilot was telling her the same kind of thing at a far lower cost. Nobody asked what the two technicians were actually saying. "Back at the depot" meant the app only worked where the old spreadsheet already did.
Even at that stage, a mobile login fix and a one-month delay would have saved the launch. Going live anyway cost the team its credibility with 140 technicians, which took far longer to win back.
The meeting where it was still fixable
The real fork came eight months earlier, in the first requirements meeting. Around the table sat Sofia, two developers, the dispatch manager and the head of operations. There were no technicians in the room.
The dispatch manager described how technicians worked, and he was confident. He'd been a technician himself, eleven years before. Requirement 4.2 reads: "Technicians will update job status in real time."
Everyone nodded, and the assumption underneath it never got said out loud: that technicians would have a usable screen and a signal at the moment they finished a job.
Checking that assumption would have taken one morning. Sofia could have spent it riding along with two technicians on a normal day.
The same kind of gap ran through the Mars Climate Orbiter loss. The mishap board's report traced the root cause to a unit mismatch where two pieces of software met and found that the checks around that handoff never confirmed it matched the specification.
What you'd do differently
You can't attend every requirements meeting with a field trip. You can make sure no project leaves that meeting with its biggest assumption unspoken. Run these five questions before anyone writes a line of code:
- Who will use this, by name, and has anyone on the team watched them work?
- Where will they be, and what will be in their hands, when they use it?
- What are they using today, and why would they stop?
- Which sentence in the requirements, if it turned out to be wrong, would sink the whole project?
- Who in this room is speaking for the users, and when did they last do the job?
Then send one person from the project team to spend half a day with the users before the requirements are signed off. Write down three things they saw that surprised them, and read them out at the next meeting.
Finally, make one rule for the pilot: any comment that suggests people will work around the product goes straight to you. Those comments are rarely about training.
Your version of this
It happens more than anyone likes to admit. Pendo's analysis of product usage across 615 software subscriptions found that 80% of features were rarely or never used.
Sofia's team rebuilt the status screen for phones, added offline mode, and spent a week on site with technicians first. Weekly use reached 96 technicians three months later.
Find the requirements document for the project you're starting next. Highlight the one sentence that assumes something about the people who'll use it. Then go and watch one of them work before the next meeting.